Woodward Avenue Water Treatment Plant Upgrades – Contract 1

Recent Bennett Construction Group Project
Bennett Built
Contact Value: $20,000,000.00
A group of construction workers wearing hard hats and high-visibility clothing on a job site.
A pumping station featuring extensive pipeline infrastructure and engineering components.
A close-up view of composite materials and pipes used in construction.
Two workers in safety gear are inspecting equipment at a construction site.
A construction site featuring various building materials and soil.
A set of steel stairs featuring grey composite materials, showcasing modern construction design.
A large wheel from construction machinery used in water treatment plant projects.
Several construction workers are collaborating on a brick wall.
A Caterpillar machine working on a construction site.
A collection of construction materials including pipes and metal components used in engineering.
A construction site showcasing different building materials like metal, concrete, and pipes.
A set of grey metal stairs featuring a sturdy handrail.

Scope of Work

Rapid mixing tank work including installation of an additional chemical (PACl) injection feed line; and, replacement of 8 rapid mixers including the motor, shaft and agitator along with new power wiring, conduit and supports for the rapid mixers.

Flocculation tank work including replacement of 24 flocculation mixers including the motor, shaft and agitator along with new power wiring, conduit and support for the flocculation mixers; and, structural/process repairs within the flocculation tanks, including repairs to cracks, spalling and corrosion on the tanks base slab, walls, roof and expansion joints.

Filter building work including removal of GAC media in all 23 filter sand installation of new GAC media, topping up sand media; replacement of settled water and wash water sluice gates and hydraulic actuators for all 24 filters (24 each x 2 = 48 total); replacement of backwash valves and electrical actuators for filters 1 to 12; surface preparation and repainting of filter piping, fittings, venturi flowmeters for all 24 filters; replacement of all couplings in the filter piping gallery

Filter 7 work including removal and replacement of underdrain with new underdrain, sand and GAC media

Chemical/Lower Stores Building work including replacement of the single brick façade

Replacement of seven (7) clear well gates in a live system.