Squamish Waste Water Treatment Plant Bar Screen Upgrades
Recent Bennett Construction Group Project
Contract Value: $500,000.00
- Demolition and disposal of existing concrete, process mechanical piping, electrical and instrumentation equipment
- Temporary work to keep the treatment plant operational at all times
- New concrete work to raise the existing channels and pouring of new channel for a new fine step screen and wash press system
- New stainless steel process piping and associated electrical and instrumentation work
- Installation of new stainless steel bustle piping and instrumentation
- Installation of grit classifier