G.E. Booth WWTP Tox 4 Rehabilitation & High Pressure Pipe Modifications
Recent Bennett Construction Group Project
Owner: Region of Peel
Contract Value: $6,000,000
Scope of Work:
- Demolition of the existing emergency generator ancillary equipment.
- Design, fabrication and installation of new high pressure cake piping systems to TSSA requirements.
- Complete replacement of fluidized bed incinerator dome.
- Design, fabrication and installation of the cross over duct systems for incinerator 4 with 86" 316L S.S. shell
- Removal of the existing primary heat exchanger and lower plenum for TOX 4
- Installation of a pre-purchased new primary heat exchanger (including lower plenums) for TOX 4
- Removal of the existing primary heat exchanger upper plenum and installation of the pre-purchased heat exchanger upper plenum
- Fabrication and installation of new plenum connections between the Radiative Recuperator and the Quencher Systems
- Fabrication and installation of new warm-air lower 90 between the PHE lower plenum
- The design and installation of two expansion joints (86" and 56")
- Modifications to the cooling air system
- Modifications to the quencher water supply
- Construction or New roof opening and roofing system