Brantford Treatment Plant Upgrade
Recent Bennett Construction Group Project
Start Date: November 2008
Value: $58,623,000.00
Construct upgrades to Holmedale Water Treatment Plant with rated capacity of 100,000m3/day including:
- New three-story admin building
- New treatment facility including two clearwells, two blackwash water wells, eight filters, vertical turbine pumps, UV disinfection chem. systems and associated piping, valves and appurtenances
- Modifications to existing Pre-Treatment facility to convert chlorine contact tanks to ozone contact tanks
- Modify the existing lean-to structure to house additional chemical equipment, demolish (piping, valves and appurtenances to construct new piping and an enclosure/room in basement)
- New HL Pumping Station complete with wet wells and horizontal centrifugal pumps and associated piping, valves and appurtenances and electrical equipment
- New Transformer station including: stand-by power supply, yard piping, site works, Pre-selected equipment (Ozone system, LOX system, UV reactors), demolition of old works